What is the 
total 
charge
 to the statement of profit or loss in respect 
of the 
decommissioning 
for the year ended 
30 June 20X5

A. $453,600 
B. $725,760 
C. $800,000 
D. $2,268,000 


Ex5 
Answer B 
The cost of the decommissioning is assumed to be an obligation for the 
company. An amount should be included in the cost of the asset when it is 
first recognised (1 July 20X4). 
The amount to include in the cost of the asset for decommissioning costs is 
the present value of the expected future decommissioning costs. The present 
value is calculated by multiplying the expected future cost by a discount 
factor, which in this case is the discount factor for Year 5 (20X9) at 12%. 
$4 
million x 0.567 = $2.268 million. 
Therefore: 
Debit:
Cost of asset 
$2.268 million 
Credit:
Provision for decommissioning costs 
$2.268 million 
The asset is depreciated on a straight-line basis over five years. 


Ex5 
In addition, the decommissioning cost should be increased to $4 million by the end of 
Year 5. This is done by making a finance charge each year. This is charged at the cost 
of capital (12%) and applied to the balance on the provision account. The finance 
charge for the year to 30 June 20X5 is 12% x $2.268 million = $272,160. 
Debit:
Finance charge (expense) 
$272,160 
Credit:
Provision for decommissioning costs
$272,160 

Depreciation charge ($2,268 million/5 years) 
453,600 
Finance charge
272,160 
Total charge 
725,760 
If you selected A, you have included the depreciation without the finance cost. If you 
selected C, you have just spread the present value of the dismantling over 5 years. If 
you selected D, you have expensed the whole asset value. 


Ex5 
On 1 October 20X3, Xplorer commenced drilling for oil from an undersea oilfield. The 
extraction of oil causes damage to the seabed which has a restorative cost (
ignore 
discounting) of $10,000 
per million barrels of oil extracted. Xplorer extracted 250 
million barrels of oil in the year ended 30 September 20X4. 
Xplorer is also required to dismantle the drilling equipment at the end of its five-year 
licence. This has an estimated cost of $30 million on 30 September 20X8. Xplorer’s cost 
of capital is 8% per annum and $1 has a present value of 68 cents in five years' time. 

Download 0,83 Mb.

Do'stlaringiz bilan baham:
1   2   3   4   5   6   7   8   9   ...   18




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©hozir.org 2024
ma'muriyatiga murojaat qiling

kiriting | ro'yxatdan o'tish
    Bosh sahifa
юртда тантана
Боғда битган
Бугун юртда
Эшитганлар жилманглар
Эшитмадим деманглар
битган бодомлар
Yangiariq tumani
qitish marakazi
Raqamli texnologiyalar
ilishida muhokamadan
tasdiqqa tavsiya
tavsiya etilgan
iqtisodiyot kafedrasi
steiermarkischen landesregierung
asarlaringizni yuboring
o'zingizning asarlaringizni
Iltimos faqat
faqat o'zingizning
steierm rkischen
landesregierung fachabteilung
rkischen landesregierung
hamshira loyihasi
loyihasi mavsum
faolyatining oqibatlari
asosiy adabiyotlar
fakulteti ahborot
ahborot havfsizligi
havfsizligi kafedrasi
fanidan bo’yicha
fakulteti iqtisodiyot
boshqaruv fakulteti
chiqarishda boshqaruv
ishlab chiqarishda
iqtisodiyot fakultet
multiservis tarmoqlari
fanidan asosiy
Uzbek fanidan
mavzulari potok
asosidagi multiservis
'aliyyil a'ziym
billahil 'aliyyil
illaa billahil
quvvata illaa
falah' deganida
Kompyuter savodxonligi
bo’yicha mustaqil
'alal falah'
Hayya 'alal
'alas soloh
Hayya 'alas
mavsum boyicha


yuklab olish