Karerning hajmi, o‘lchamlari, ishlab chiqarish unumdorligi va karerning xizmat qilish muddatini hisoblash. Vk = V1 + V2 + V3
Vk – karer hajmi, m3 V1 – asosi S = Lm bo‘lgan prizma hajmi, m3 S – karer tubi yuzasi, m2 L – yotqiziqning yotishi bo‘yicha uzunligi, m.
m – yotqiziqning gorizontal qalinligi, m.
V1 = L • m • Hk Hk– karer chuqurligi, m
V2 – hajmning to‘rt tomoniga jipslashib turgan prizmaning uchburchak kesmaning yig‘indi hajmi
V2 = P Hk2 ctg αsr P – yotqiziqning perimetri P = 2 (L + m) V3 – karerning burchakdagi uchastkalarida joylashgan aloxida qismlarga bo‘lingan konusning yig‘ma hajmi (V3va V3″ ) m3 V3 = Hk3 ctg2αsr αsr – ish olib borilmaydigan bortning qiyalik burchagi
Karer yig‘indi hajmi
Vk = S Hk + P Hk2 ctg αsr + Hk3 ctg2αsr S = Lm =250 • 50 = 12500 m2 P = 2 (L + m) = 2 • (250 +50)= 600 m
Vk = S Hk + P Hk2 ctg αsr + Hk3 ctg2αsr =12500 • 400 + • 660 • 4002 • ctg 65o + • 4003 • ctg2 65o =6 252,83 mingm3 Karer maydoni uzunligi
Lk = L + 2Hk • ctg αsr = 250 + 2 • 400 • ctg 65o = 2268 m
Yuqori qismi bo‘yicha karer kengligi
Bk = m + 2Hk • ctg αsr = 50+ 2 • 400 • ctg 65o = 418 m
Karer konturidagi foydali qazilma hajmi
Vpi= S (Hk – hn)=12500• (400- 5) = 361691 m3 Karer konturidagi foydali qazilma sanoat zaxirasi
Qpi = Vpi ρi ηi = 361691• 3.0 • 0.93= 9733880 t
Karer konturidagi tog‘ jinsi hajmi
Vp = Vk – Vpi =6 252,83 – 361691= 367298 m3 O‘rtacha qoplovchi tog‘ jinsi koeffitsienti
ksr = Vp / Qpi = 167298240 / 77338800= 2.1 m3/t
Qoplovchi tog‘ jinsi bo‘yicha karerning ishlab chiqarish unumdorligi
Pv = Ppi ksr kn = 5 • 104• 2.1• 1.2= 12.6 • 104 = 3.648 • 105m3/yil
kn = 1.1 ÷ 1.3 Kon massasi bo‘yicha karerni ishlab chiqarish unumdorligi
Pgm= Ppi + Pv = 3.6 • 105 • +126 • 104 = 336 ming m3/yil
Karerning foydali qazilma bo‘yicha sutkalik unumdorligi
Ppis= Ppi / Tg = 3.6• 105 / 350 = 1343 t/sutka
Tg = 350 kun
Qoplovchi tog‘ jinsi bo‘yicha karerning sutkalik ish unumdorligi
Pvs = Pv / Tg = 3.648 • 105 / 350 = 2550 m3/sutka
Foydali qazilma va qoplovchi tog‘ jinsi bo‘yicha karerning smenalik ishlab chiqarish unumdorligi
Ppism = Ppis / nsm = 13433 / 2 = 7543 t/smena
Pvsm = Pvs / nsm = 25500/ 2 = 12250m3/smena
nsm = 2 Karerni xizmat qilish muddati
Tsl = Ts + Te + Tz Te = Qpi / Ppi = 80030 / 5 • 105 =1.6 yil
Kapital transheya hajmini hisoblash
Kapital transheya hajmi
V1 = bt ht2 / 2i bt – transheya asosi kengligi
ht – transheya chuqurligi
i – kapital transheya qiyaligi
V1 = 35 • 152 / 2 • 0.038 = 126.455 m3 Piramida hajmi
Vt = 124.625 + 2 • 10 = 144.625 m3 Qirqim transheya o‘tish ko‘rsatkichlarini va parametrlarini hisoblash
12 soat
2 smena
dc = 250 mm
Hu = 15 m
Skvajina uzunligi
Lc = Hu + lper = 5 + 1,8 = 6.80 m
Perebur uzunligi
lper = 11dc = 11 • 0,25= 2.75 m
Kolonkali zaryad uzunligi
lzar = Lc – lzab = 6,8– 4,7 = 4.9m
Zaboyka uzunligi
lzab = 0,27Lc = 0,27 • 6.8 = 1.836 m
Qatordagi zaryad massasi
Qzo = ρlzar = 21,37 • 4.9 = 106 kg
Qzv = ρlzar = 21,37 • 4.9= 106 kg
Zaryad massasining o‘rtacha qiymati
Qzs = = 106 kg
Bitta zaryad yordamida ajratib olinadigan tog‘ jinsi hajmi
V1zar = Qzs / qp = 106/ 0.9 = 116 m3 Bitta skvajina qatori yordamida ajratib olinadigan tog‘ jinsi hajmi
V5zar = 116• 5 = 590 m3 Zaboyda yuklash sharoitida ekskavatorni ish unumdorligi
Texnik ish unumdorligi
Pet = E kcn = • 5 • • 0.7 = 410 m3/soat
Ekskavatorni smenali ekspluatatsion ish unumdorligi
Pesm = Pet Tsm ki = 410• 12 • 0.75 = 4145m3/smena
Ekskavatorni sutkalik ish unumdorligi
Pesut = Pesm nsm = 4145 • 2 = 8360 m3/sut
Ekskavatorni oylik ish unumdorligi
Pemes = Pesut •27 = 8360 • 27= 212510 m3/mes
Transheyani o‘tish tezligi
V = = 212510 / 629 = 341 m/mes
St = Hy (Bt + Hy ctgα)= 5 • (35 + 5• ctg 65o)= 540 m2 Bt = 35 m Ht = Hy Ish olib boriladigan va ish olib borilmaydigan bortlar konstruksiyasi
Ish olib boriladigan bortning balandligi
Nrb = Nu nru = 15 • 23 = 345 m
Kon massasini avtomobil transportiga yuklashda ishchi maydon kengligi
SHrp = Vr + S + T + S + Z + SHvb = 23 + 2 + 12 + 2 + 2.85 + 4 = 45.85 m
Vr – tj uyumi kengligi
S – transport yo‘lagi va uyumlarning quyi brovkasi orasidagi xavfsizlik kengligi (2 – 3 m)
T – transport yo‘lagi
S – xavfsizlik oralig‘i (1.5 – 2 m)
Z – prizmaning emirilish kengligi
Z = Hy (ctgy α – ctg α) = 15 • (ctgy 65o – ctg 75o) = 2.85 m
Ish olib boriladigan bort qiyaligining gorizontal qo‘yilgan o‘lchami
Srb = Hy ctg α nru + SHrp (nru - 1) = 15 • 0.46 • 23 + 45.85 • (23 - 1)= 1167.4m
Karerning ish olib boriladigan bortining tangens burchagi
tg φ = Hrb / Crb = 345 / 1167.4 = 0.29 = tg 16o Ish olib borilmaydigan bort balandligi
Nnb = Nu nnu = 15 • 23= 345 m
Ish olib borilmaydigan bort qiyaligining gorizontal qo‘yilgan o‘lchami
Snb =nnu(Nuctgαy+vs)+(nnu – 1)vb=23 • (15 • ctg 65o+5)+(23 - 1) • 5= 122 m
vs – s’ezd kengligi
vb ≥ Hy = • 15 = 5 m
Ish olib borilmaydigan bort qiyalik burchagining tangensi
tg α = Hnb / Snb = 345/ 384 = 0,9 = tg 42o Qazib olish tizimining elementlari va ularning parametrlari Qazib olish tizimining elementlariga to'siqlar, to'siq va ochiq chuqurning ishchi old qismi, ochiq karerning ish maydoni, ishchi platformalar, transport va xavfsizlik bermalari kiradi. Oddiy konstruktsiyali konlarni o'zlashtirish tajribasi shuni ko'rsatadiki, 3-5 va 8-12,5 m3 sig'imli ekskavatorlar uchun to'siqning oqilona balandligi mos ravishda 11-14 va 16-19 m oralig'ida.
EKG-5 va EKG-5A mexanik kuraklari va temir yo'l transportidan foydalanganda ishchi platformaning kengligi yumshoq jinslarda mos ravishda 26-31 va 29-33 m, toshloqlarda 39-52 va 45-60 m. Avtotransport vositalaridan foydalanilganda, ishchi platformaning kengligi yumshoq va qattiq jinslarda mos ravishda 23-30 va 37-52 m.
To'siqning old qismi tog'-kon ishlarini ishlab chiqarish uchun tayyorlangan uzunlik bo'ylab to'siqning bir qismidir. To'siqning old qismini tayyorlash tog'-kon va transport uskunalarining ishlashini ta'minlash uchun to'siqda kerakli kenglikdagi ishchi platformani yaratish va transport va energiya kommunikatsiyalarini ta'minlashdan iborat. Ish jabhalarining umumiy uzunligi ochiq qazib olinadigan ish jabhasi bo'lib, u o'ta og'ir to'siqlarning ish old tomonlari uzunligi bilan o'lchanadigan va tog'-kon dastgohlarining ish old tomonlari uzunligi bilan o'lchanadigan konga bo'linadi.
Ishchi pog`ona frontining uzunligi Lf.y va uning borish tezligi vf ekskavatorlarning yillik ish unumdorligi bilan ishlashini ta'minlashi kerak.
=5*200*9,2/4=2300 м3 bu yerda Ne.y - berilgan pog`onadagi ekskavatorlar soni.
Ikki yoki undan ko'p ekskavator to'sig'ida ishlaganda, to'siqning ishchi old qismi alohida ekskavator bloklariga bo'linadi, ularning uzunligi EKG-5 va EKG-5A ekskavatorlari uchun mos ravishda 500-600 va 1000-1400 m ni tashkil qiladi. avtomobil va temir yo'l transportidan foydalanish.
Yassi er va karerning har ikki tomonining rivojlanishi bilan, ishchi zonaning maydoni
Sр.з=(hр.з(ctgв+ ctgл)+Шд) = =(25(ctg400+ctg450)+40)*200=24*2.1+40=90.4 м2 bu yerda hр.з - ish maydonining balandligi, m; в, л – konning osilgan va yotib turgan tomoni tomondan ishchi tomonlarning qiyalik burchagi, grad; Шд – ochiq chuqurning pastki kengligi, m; - to'siqlar old qismining o'rtacha uzunligi, m.
Karerning ish maydonida joylashgan ekskavator bloklari soni
=95/40*0,9*0,75=1,6=2 шт
bu erda Ko = 0,85-0,93 - ishchi zonada qiyaliklarning yonbag'irlari mavjudligini hisobga olgan holda koeffitsient; Ortiqcha (ishlamaydigan) birliklar mavjudligini hisobga olgan holda f=0,7-0,8 koeffitsienti.
Ish maydoni balandligi:
bu erda B - sirtdagi ochiq chuqurning dizayn kengligi, m;
В = Шд+ 2*Hk *ctgβ = 40 +400 = 440 м;
Нр.з. =(440-40)/(3,08+3,08)≈ 67 м
bular. Ishchi pog`onalar soni 114/15=7.6 8ta pog`onaga teng bo`ladi