DW: Tell us about your implementation.
RL: We had problems delivering H-46s on time. The H-46 is a 25-to 30-year-
old Boeing helicopter used extensively in the Marine Corps as part of their
assault support role. Because the airplane is so old and in frequent need of
maintenance, anything over a single-digit number of airplanes on our hangar
deck meant that you took a shadow off the flightline. If you took a shadow
off the flightline, that meant they didn’t have an airplane to do their mission.
Our negotiated norm for turnaround time was 130 days, and on average we
were somewhere between 190 and 205 days.