Lessons learned register.
Described in Section 4.4.3.1. The lessons learned register is updated with information
on challenges encountered and how they could have been avoided as well as approaches that worked well for
acquiring resources.
u
u
Project schedule.
Described in Section 6.5.3.2. Changes to the project schedule may result from the availability
of required resources.
u
u
Resource breakdown structure.
Described in Section 9.2.3.3. Resources acquired during this process are
recorded in the resource breakdown structure.
u
u
Resource requirements.
Described in Section 9.2.3.1. Resource requirements documentation is updated to
reflect resources acquired for the project.
u
u
Risk register.
Described in Section 11.2.3.1. New risks identified during this process are recorded in the risk
register and managed using the risk management processes.