information regarding resources that will be acquired from outside the project. This includes information on how
procurements will be integrated with other project work and stakeholders involved in procuring resources.
Described in Section 7.3.3.1. The cost baseline provides the overall budget for the project activities.
��
331
9.3.1.2
PROJECT DOCUMENTS
Project documents that can be considered as inputs for this process include but are not limited to: