Scope management plan.
Described in Section 5.1.3.1. The scope management plan documents how the
project and product scope will be controlled.
u
u
Requirements management plan.
Described in Section 5.1.3.2. The requirements management plan describes
how the project requirements will be managed.
u
u
Change management plan.
Described in Section 4.2.3.1. The change management plan defines the process
for managing change on the project.
u
u
Configuration management plan.
Described in Section 4.2.3.1. The configuration management plan defines
those items that are configurable, those items that require formal change control, and the process for controlling
changes to such items.
u
u
Scope baseline.
Described in Section 5.4.3.1. The scope baseline is compared to actual results to determine if
a change, corrective action, or preventive action is necessary.
u
u