17.12 Project Stages
and Cash Flow Estimation
555
Cash Flows During the Project’s Operating Life
Operating cash fl ows can be estimated using equation 17-4. The diffi
culty is determining the
amounts for sales, costs, depreciation, taxes, and net working capital changes in order to enter
these into the calculations.
A project with the main purpose of reducing costs should have a presumed impact on
sales of zero. Expected cost savings can be derived from engineering estimates or production
management techniques. Suppliers can often estimate the potential cost savings from new
machines
or processes, but these sales claims may be untrustworthy; the careful manager
runs independent tests and trial runs, preferably at the plant that will house the new project,
to verify any claims.
One asset often replaces another in cost-saving projects. This can involve a diff erence in
depreciation schedules between the old and new asset (not to mention salvage value diff er-
ences), which the analyst must incorporate into the analysis. More will be said about this point
later in the chapter when we review an example.
Revenue enhancing or revenue sustaining projects build or protect a fi rm’s competit-
ive advantage or extend its market penetration. Market researchers can provide detailed data
about new products or features and the costs to develop them in order to help the fi nancial
analyst construct cash fl ow estimates. Such research may include sales forecasts or informa-
tion
on price, quantity, and quality trends in the market segment. If the project concerns one
of the fi rm’s current products, the production staff can often provide data to estimate the cost
implications of greater sales. If the project involves a new product off ering, engineers or the
production staff should be able to provide production cost estimates. Depreciation expense
can be estimated from the estimated initial investment outlay for the property or equipment
needed for the project.
Net working capital may change over the course of the project’s life. Operating cash fl ow
estimates must refl ect these changes in net working capital.
Salvage Value and NWC Recovery at Project Termination
If the project is expected to have a defi nite
life span, the analysis must consider the salvage
value of the project’s assets. Any increases in net working capital in the course of a project
are generally assumed to be recovered by the fi rm and converted to cash at the project’s
end.
Any property or equipment that is expected to be sold, either for use by someone else or
for scrap, will generate infl ows. The cash fl ow for the sale will have to be adjusted to account
for tax implications if the asset’s selling price diff ers from its book value. Book value (BV)
represents an asset’s original cost less accumulated depreciation. At the end of a project, if
the selling price of an asset equals its book value there is no need for tax adjustments; the
after-tax cash fl ow equals the selling price. If the asset’s selling price exceeds its book value,
then the asset was depreciated too quickly on the fi rm’s books.
The amount of the recovered
depreciation (Price − BV) is taxed at the fi rm’s marginal tax rate for ordinary income. Thus,
the tax owed the government is
T
(Price − BV). The total after-tax proceeds will be Price −
T
(Price − BV); that is, the selling price less the tax obligation. If the selling price is less than
the asset’s book value, the fi rm suff ers a loss. This loss refl ects failure to depreciate the asset’s
book value quickly enough. The fi rm’s taxable income is reduced by the amount of the loss,
and taxes will be reduced by
T
(Price − BV).
If
T
(Price − BV) is positive, the fi rm owes taxes, reducing the after-tax proceeds of the
asset sale; if
T
(Price − BV)
is negative, the fi rm reduces its tax bill, increasing the after-tax
sale proceeds. When
T
(Price − BV) is zero, the transaction causes is no tax adjustment to be
made. Thus, a general relationship for the after-tax salvage value is the following:
After-tax salvage value = Price −
T
(Price − BV)
(LE17-1)
Let’s look at an example. Assume an asset originally cost $100, had an expected life of ten
years, and was depreciated on a straight-line basis. Seven years later, the fi rm must determine
the after-tax cash fl ow from selling the asset if the selling price is (a) $50, (b) $30, or (c) $15.
Assume the marginal tax rate for ordinary income is 34 percent.
556
C H A PT E R 1 7 Capital Budgeting Analysis
First, we must determine the asset’s book value, and then equation LE17-1 can be used
to compute cash fl ows for three situations. With an original cost of $100
and straight-line
depreciation over ten years, its yearly depreciation expense is $100∕10 = $10. As seven years
have passed, accumulated depreciation is now $70 (7 × $10∕year), so the asset’s book value is
$100 minus $70, or $30.
If the asset’s sale price is $50, the fi rm has recovered some past depreciation and it must
reduce the salvage value cash fl ow by the resulting tax liability. The after-tax salvage value is
the following:
Price −
T
(Price − BV) = $50 − 0.34($50 − $30) = $43.20
If the asset’s sale price is $30, this price equals the book value. According to equation LE17-1,
the after-tax salvage value is $30: Price −
T
(Price − BV) = $30 − 0.34($30 − $30) = $30.
If the asset’s sale price is $15, the fi rm suff ers a loss, as the price is below book value.
This means the salvage value cash fl ow will rise above $15 by the amount of the subsequent
tax savings. The after-tax cash fl ow equals the following:
Price −
T
(Price − BV) = $15 − 0.34($15 − $30) = $20.10.
By their nature, after-tax salvage values are diffi
cult to estimate since the salvage value and
expected future tax rate are uncertain.
As a practical matter, if the project termination is many
years in the future, the present value of the salvage proceeds will be small and inconsequential
to the analysis. If necessary, however, the analyst can develop a salvage value forecast in two
ways. First, one could tap the expertise of those involved in secondary market uses of the asset.
Second, one could forecast future scrap material prices for the asset. Typically, the after-tax
salvage cash fl ow is calculated using the fi rm’s current tax rate as an estimate for the future
tax rate.
The problems of estimating values in the distant future are diffi
cult
when the project
involves a major strategic investment that the fi rm expects to maintain over a long period of
time. In such a situation, the fi rm may estimate annual cash fl ows for a number of years (say,
ten years) and attempt to estimate the project’s value as a going concern at the end of this time
horizon. One method the fi rm can use to estimate the project’s going-concern value is the
constant dividend growth model discussed in Chapter 10:
Price
horizon
=
Dividend
horizon + 1
r
−
g
(LE17-2)
The “salvage value” of the project is its going-concern value at the end of the time hori-
zon; the dividend is its expected operating cash fl ow one year past the horizon. The required
rate of return,
r
, is the project’s required return. The expected growth rate,
g
, is the analyst’s
estimate of the constant growth rate for operating cash fl ows after the horizon.