Geothermal handbook: PlanninG and Financing power Generation t e c h n I c a L r e p o r t 2 / 2



Download 5,56 Mb.
Pdf ko'rish
bet150/177
Sana08.02.2022
Hajmi5,56 Mb.
#435170
1   ...   146   147   148   149   150   151   152   153   ...   177
Bog'liq
FINAL Geothermal Handbook TR002-12 Reduced

Government Support case |
The government provides grants (or capital subsidies) covering 50 
percent of the project’s investment costs in Years 1 through 3, and stops the grant support only when 
exploratory drilling reaches a positive result. Given that the initial phases prior to exploratory drilling 
are relatively low-cost surface surveys, the first three years of the project are high on risk but not so 
high on costs. The amount of the total grant contribution is US$ 14 million. Still, the grant support 
substantially increases the return on the private investor’s equity, bringing it above the required return 
of 25 percent.
Under new circumstances, the project passes the positive NPV test (Table 3.3).
T A B L E 3 . 3
Case with Public Support
PARAMETER
VALUE
Total Investment Cost of Project
US$ 196,000,000 
Investment Cost per Megawatt
US$ 3,920,000 / MW
Government Grant Undiscounted Value
55
US$ 14,000,000
Required Return on Equity
25%
Interest Rate of the Loan
6%
Equity Share in Capex (from year 2 on)
30%
Tax Rate
20%
Capacity Factor
90%
O&M, including Labor 
US$ 10,192,000 / yr
Levelized Cost of Energy 
US$ 0.05 / kWh
Tariff 
US$ 0.12 / kWh
Return on Equity
27.8%
NPV 
US$ 3,539,420
Source | Authors.
From the government’s perspective, a grant of US$ 14 million or less to leverage a US$ 196 million 
project may be a contribution well worth considering, if this leads to affordable, reliable power supply. 
It should be noted that, in addition to improving the rate of return on equity, government support during 
the crucial first stages of project development may reduce the private investor’s perception of risk and 
thus lower the hurdle rate of return on equity. The reduced cost of capital may in turn bring the required 
tariff down. For example, applying a 20 percent hurdle rate for the return on equity in the Government 
Support Case instead of the rate of 25 percent used in the Base Case renders the tariff of US$ 0.12 per 
kWh unnecessarily high. A tariff of US$ 0.10 per kWh, which results in a 21 percent rate of return on 
equity, may be sufficient for the private investor, whose NPV remains positive.
55
The present value of the grant would be lower since the grant is disbursed over a period of three years.


107
C h a p t e r 3
The impact of the reduction in the cost of equity leading to a reduction of the tariff by 2 cents per kWh 
can be illustrated by calculating the present value of the reduction in the tariff over the project life. If, 
for example, instead of providing grant support in the early years of the project, the government chose 
to subsidize the tariff for geothermal energy once the plant was in operation, it would be committing 
to a greater expenditure of public money than the value of the grant noted above. Over the plant 
operation period of 25 years (assuming that a flat tariff
56
is contractually secured for the same period), 
the difference of 2 cents per kWh translates into an additional public funding commitment of US$ 46.9 
million (present value discounted at the weighted average cost of capital applied to the project).

Download 5,56 Mb.

Do'stlaringiz bilan baham:
1   ...   146   147   148   149   150   151   152   153   ...   177




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©hozir.org 2024
ma'muriyatiga murojaat qiling

kiriting | ro'yxatdan o'tish
    Bosh sahifa
юртда тантана
Боғда битган
Бугун юртда
Эшитганлар жилманглар
Эшитмадим деманглар
битган бодомлар
Yangiariq tumani
qitish marakazi
Raqamli texnologiyalar
ilishida muhokamadan
tasdiqqa tavsiya
tavsiya etilgan
iqtisodiyot kafedrasi
steiermarkischen landesregierung
asarlaringizni yuboring
o'zingizning asarlaringizni
Iltimos faqat
faqat o'zingizning
steierm rkischen
landesregierung fachabteilung
rkischen landesregierung
hamshira loyihasi
loyihasi mavsum
faolyatining oqibatlari
asosiy adabiyotlar
fakulteti ahborot
ahborot havfsizligi
havfsizligi kafedrasi
fanidan bo’yicha
fakulteti iqtisodiyot
boshqaruv fakulteti
chiqarishda boshqaruv
ishlab chiqarishda
iqtisodiyot fakultet
multiservis tarmoqlari
fanidan asosiy
Uzbek fanidan
mavzulari potok
asosidagi multiservis
'aliyyil a'ziym
billahil 'aliyyil
illaa billahil
quvvata illaa
falah' deganida
Kompyuter savodxonligi
bo’yicha mustaqil
'alal falah'
Hayya 'alal
'alas soloh
Hayya 'alas
mavsum boyicha


yuklab olish