Bir qavatli sanoat binosi qurilishining taqvimiy grafigi
№
§§
YAMvaN
(ENiR)
Ishlarning ro‗yhati
O‗lchov
birligi
Ishlar
hajmi
Vaqt
me‘yori,
kishi-soat
Mehnat-
talablik,
kishi-kun
Zveno tarkibi
Smena
soni
Ish
muddati,
kun
Ish
grafigi
1
2
3
4
5
6
7
8
9
10
11
1
E2-1-5,
E2-1-24
D-271 S-80 buldozerida o‗simlik
qatlamini kesish va maydonni
tekislash
1000 m
2
66x98=
6,5
1,9 + 1,44
=3,34
2,7
Mashinist
5md-1
1
3
2
E2-1-7,
t.4, p.2a
Tig‗i yaxlit bo‗lgan cho‗mich hajmi
0,65 m
3
sig‗imli draglayn
ekskavatorida
1 guruhli gruntni transportga ortib
qazish
100 m
3
17,35
3,3
7,16
Mashinist
6md-1, mashinist
yordamchisi
5md-1
1
4
3
E2-1-7,
t.4, p.2g
Tig‗i yaxlit bo‗lgan cho‗mich hajmi
0,65 m
3
sig‗imli draglayn
ekskavatorida 1 guruhli gruntni
handaq chetiga to‗kib qazish
100 m
3
59,61
2,8
20,86
--// --
1
11
4
E2-1-15,
t.2, p.5
D-271 S-80 buldozerida handaq
tubini tozalab (ortiqcha gruntni
qirqish),
30 m masofaga surish
100 m
3
3,67
0,69+ 2x0,6
= 1,89
0,86
Mashinist
5md-1
1
1
5
E2-1-7,
t.4, p.2g
Buldozer yordamida tozalangan
gruntni ekskavator bilan to‗kish
joyiga (otval) tashlash
100 m
3
3,67
2,8
1,28
Mashinist
6md-1, mashinist
yordamchisi
5md-1
1
1
6
E2-1-15,
t.2, p.5
20 m masofaga gruntni to‗kish
joyiga surish
100 m
3
8,82
0,6x2 = 1,2
1,33
Mashinist
5md-1
1
1
7
E2-1-15,
t.2, p.5
Vaqtinchalik to‗kish joyidan 5 m
masofaga gruntni to‗kish joyiga
surish
100 m
3
15,5
0,6/2 = 0,3
0,58
--// --
1
1
8
E2-1-21,
t.2, p.2
D-271 S-80 buldozerida gruntni 25
m masofaga surish bilan poydevor
yonini grunt bilan qayta to‗ldirish
100 m
3
59,61
0,39+0,2x4
= 1,19
8,87
Mashinist
5md-1
1
9
9
E2-1-58,
t.2, p. 2b
Gruntni 25 m masofaga qo‗lda
surish bilan poydevor yonini grunt
bilan qayta to‗ldirish
1 m
3
400
0,51
25,5
Er qazuvchi
2md-2, 1md-2
1
7
10
E2-1-59,
t.3, p. 2a
Elektr zichlagichda gruntni zichlash
100 m
2
298
1,9
70,77
Er qazuvchi
3md-4
1
18
11
--
Ortiqcha gruntni MAZ-205
avtosamosvalda 5 km masofaga
tashib ketish
1 m
3
1735
--
49
Avto xaydovchi-lar 3
sinf – 14 kishi
1
3
12
E4-1-27,
t.2, p. 1
Poydevor bloki ostiga beton
to‗shamasi uchun taxtadan qolip
tayyorlash
1 m
2
52,6
0,65
4,27
Duradgor
4md-1,
2md-1
1
2
13
E4-1-37,
t.2, p. 1
Poydevor bloki ostiga beton
to‗shamasi uchun qorishma quyish
1 m
3
26,4
0,44
1,45
Betonchilar
4md-1, 2 md-1
1
1
14
E4-1-27,
t.2, p. 1v
Poydevor bloki ostiga beton
to‗shamasi uchun taxtadan
qoliplarni ko‗chirib olish
1 m
2
52,6
0,2
1,31
Duradgor
4md-1,
2md-1
1
1
15
E4-1-1, p.
9
Og‗irligi 7,5 t gacha bo‗lgan o‗rta
ustunlar ostidagi yig‗ma t/b
poydevor bloklarini montaj qilish
1 element
11
2,82
3,88
Montajchilar – 4md-
1, 3md-1, 2md-1
1
2
16
E4-1-1, p.
9
Og‗irligi 5 t gacha bo‗lgan yig‗ma
t/b poydevor bloklarini montaj
qilish
1 element
38
2,19
10,4
--// --
1
3
17
E4-1-1, p.
7
Og‗irligi 3,5 t gacha bo‗lgan
yig‗ma t/b poydevor bloklarini
montaj qilish
1 element
12
1,74
2,6
--// --
1
3
18
E3-2
Poydevor bloklarini
2 marta issiq bitum mastikasida
suvdan himoyalash qatlamini
surkash
100 m
2
3,21
11,8
4,75
Suvdan
himoyalovchi – 3md-
2
1
2
19
E4-1-4,
t.4, p.6a
Og‗irligi 8 t gacha bo‗lgan
ustunlarni montaj qilish
1 element
38
6,6
31,34
Montajchi
5md-1, 4md-1,
3md—2, 2md-1
2
3
20
E4-1-4,
t.4, p.8a
Og‗irligi 15 t gacha bo‗lgan o‗rta
ustunlarni montaj qilish
1 element
11
9,5
13,06
--// --
2
1
21
E4-1-4,
t.4, p.5a
Faxverk ustunlarini montaj qilish
1 element
12
5,85
8,8
--// --
1
2
22
E4-1-18,
t.1, p.2
Ustunlarni poydevorlar bilan
tutashgan joyini hajmi 0,1 m
3
dan
ko‗p bo‗lgan beton qorishmalarida
to‗ldirib bekitish
1 tutash-
gan joy
49
1,25
7,65
Montajchi
4md-1,
3md-1
1
4
23
E4-1-18,
t.1, p.1
Ustunlarni poydevorlar bilan
tutashgan joyini hajmi 0,1 m
3
gacha bo‗lgan beton qorishmalarida
to‗ldirib bekitish
1 tutash-
gan joy
16
0,83
1,67
--// --
1
1
24
E4-1-6
Uzunligi 6 m gacha bo‗lgan
poydevor to‗sinlarini montaj qilish
1 dona
46
2
11,5
Montajchi
5md-1, 4md-1, 3md-
2, 2md-1
2
1
25
E4-1-17
Poydevor to‗sinlari choklarini
payvandlash
1 m chok
37
0,56
2,6
Payvandchi
5md-1
1
3
26
E5-1-9
Ustunlar orasiga metall bog‗lovchi
va tirgaklarni montaj qilish
1 dona
element
58
3,5
25,4
Montajchi
5md-1, 4md-1, 3md-
2, 2md-1
2
3
27
E4-1-6
Og‗irligi 11 t gacha bo‗lgan kran
osti to‗sinlarini montaj qilish
1 dona
element
54
8
54
Montajchi
5md-1, 4md-2,
3md—2,
2
5
28
E4-1-17
Kran osti to‗sinlarining choklarini
payvandlash
1 m chok
94
0,95
11,1
El. payvandchi
5md-2
1
3
29
E4-1-18
Kran osti to‗sinlari choklarini
to‗ldirish
1 tugun
60
2,8
21
Montajchi
4md-2, 3md-2
1
5
30
E4-1-6
Uzunligi 18 m bo‗lgan tom
to‗sinlarini montaj qilish
1 element
30
8,5
31,88
Montajchi
6md-1, 5md-1,
4md-1, 3md-1,
2md-1
2
3
31
E4-1-17
Tom to‗sinlari tutashmalarini
payvandlash
1 m chok
54,82
0,95
6,51
El. payvandchi
5md-1
1
7
32
E4-1-7
Yuzasi 20 m
2
gacha bo‗lgan tom
yopmalarini montaj qilish
1 element
162
1,32
26,73
Montajchi
4md-1, 3md-2,
2md-1
2
3
33
E4-1-17
Tom yopmalari choklarini
payvandlash
1 m chok
92
0,56
6,44
El. payvandchi
5md-1
1
7
34
E4-1-19
Tom yopmalari choklarini mayda
toshli qorishma bilan to‗ldirish
100 m
chok
14,58
6,4
11,66
Montajchi
4md-2, 3md-2
1
3
35
E4-1-8
Yuzasi 10 m
2
gacha bo‗lgan devor
panellarini montaj qilish
1 dona
panel
288
3,24
116,64
Montajchi
5md-2, 4md-2, 3md-
2, 2md-2
2
7
36
E4-1-8
Yuzasi 15 m
2
gacha bo‗lgan devor
panellarini montaj qilish
1 dona
panel
14
4,2
7,4
--//--
1
1
37
E4-1-17
Devor panellari choklarini
payvandlash
1 m chok
440,6
0,56
30,84
El. payvandchi
5md-2
1
15
38
E4-1-19
Devor panellari choklarini to‗ldirish
100 m
chok
21,84
18,5
50,5
Montajchi
4md-2, 3md-2
1
12
39
E4-1-22
1
12
40
E7-16
1
8
To„rsimon taqvimiy rejalar haqida umumiy tushunchalar
Qurilishni tashkil qilishda taqvimiy rejalashtirishning ahamiyati juda katta. CHunki har bir
qurilish-montaj ishlari oldindan rejalashtirilgan hajmda va kunda belgilangan ishchilar tomonidan
bajarilgandagina bino va inshootlarni o‗z vaqtida sifatli qilib qurib foydalanishga topshirish va mahsulot
tannarxini pasaytirishga erishish mumkin. Aks holda qurilish jarayonida favqulodda tashkiliy tanaffuslar
qilishga, ko‗zda tutilmagan ayrim sarf-harajatlar qilishga to‗g‗ri kelishi mumkin. Bu esa qurilish
muddatini, qurilish mahsuloti sifatini va uning tannarxini nazorat qilish imkoniyatini bermaydi, hamda
rejada ko‗zda tutilgan ko‗rsatkichlarga erishishni xavf ostida qoldiradi. Qurilishda bunday holning yuzaga
kelmasligi uchun taqvimiy rejalar tuziladi va qurilish ishlab chiqarishi unga muvofiq olib boriladi.
Taqvimiy rejalar yuqorida aytib o‗tilganidek 3 xil: chiziqli, siklogramma va to‗rsimon grafiklar
ko‗rinishida bo‗ladi. To‗rsimon taqvimiy reja chiziqli taqvimiy rejadan o‗zining quyidagi afzalliklari
bilan ajralib turadi:
- to‗rsimon kalendar rejada qurilish-montaj ishlarining tashkiliy-texnologik bog‗liqligi va ketma-
ketligi yaqqol ko‗zga tashlanib turadi;
- to‗rsimon kalendar rejada qurilish muddatini belgilab beruvchi asosiy ishlar aniq ko‗rinib turadi;
- to‗rsimon kalendar rejaga muvofiq hohlagan paytda qurilishning necha kunga ilgarilab yoki
aksincha ortda qolayotganligini aniqlash mumkin;
-to‗rsimon kalendar rejada har bir ishning vaqt zahirasini, ya‘ni bu ishni necha kun erta yoki kech
boshlab tugatish mumkinligin aks ettirish imkoniyati bor;
- to‗rsimon kalendar reja qurilish-montaj ishlarining bajarilishini rejalashtirishda, uning
ko‗rsatkichlarini hisoblashda kompyuterlarni qo‗llash imkonini beradi va h.k.
To‗rsimon taqvimiy rejalarning ahamiyati to‗g‗risida so‗z yuritar ekanmiz, uning ilgarigi
sotsialistik ishlab chiqarish davrida ham, bugungi kunda ham juda kam qo‗llanilayotganini eslatib o‗tish
lozim. Sobiq Ittifoq davrida rejalar faqat son ortidan quvib sifatni esdan chiqarish yo‗li bilan bajarilgani
sir emas. SHuning uchun to‗rsimon taqvimiy rejalarga doimo o‗zgartirish kiritish, uni korrektirovka qilish
lozim bo‗lgan. Bu o‗z navbatida uni ishlab chiqarish uchun qo‗llash imkoniyatini birmuncha chegaralab
qo‗ygan.
Rejalashtirishning bu turi dastlab 1956 yilda AQSHda paydo bo‗ldi. Biroz keyin, ya‘ni 1958 yilda
bu mamlakatning harbiy qo‗mondonligiga qarashli maxsus loyihalash boshqarmasida to‗rsimon reja
asosida PERT tizimi ishlab chiqildi. U «Polyaris» nomli raketa kompleks qurilishi loyihasini tuzish va
tashkil qilishda qo‗llanildi. Bu to‗rsimon reja hajm jihatidan nihoyatda ulkan bo‗lib 100 mingta
«voqeani» o‗z ichiga olgan edi. Mutaxasislarning fikricha, mazkur rejalashtirish kompleks qurilishini
muddatidan ikki yil oldin qurib bitkazilishiga va sarflangan kapital sarmoyalarning samaradorligini
birmuncha oshirilishiga imkoniyat yaratgan. SHundan so‗ng AQSHda ham, qator rivojlangan
mamlakatlardagi yirik qurilishlarda ham to‗rsimon taqvimiy rejalar keng qo‗llanila boshlandi. Bizning
respublikamizda esa ular faqat 70 - yillarning o‗rtalarida ishlab chiqarishga kirib keldi.