Schedule management plan.
Described in Section 6.1.3.1. The schedule management plan may be updated to
reflect a change in the way the schedule is managed.
u
u
Schedule baseline.
Described in Section 6.5.3.1. Changes to the schedule baseline are incorporated in
response to approved change requests related to change in project scope, resources, or activity duration
estimates. The schedule baseline may be updated to reflect changes caused by schedule compression
techniques or performance issues.
u
u
Cost baseline.
Described in Section 7.3.3.1. Changes to the cost baseline are incorporated in response to
approved changes in scope, resources, or cost estimates.
u
u