baseline are incorporated in response to approved changes in scope, schedule performance, or cost estimates.
In some cases, the performance variances can be so severe that a change request is put forth to revise the
performance measurement baseline to provide a realistic basis for performance measurement.
230
Part 1 - Guide
6.6.3.5 PROJECT DOCUMENTS UPDATES
Project documents that may be updated as a result of carrying out this process include but are not limited to:
u
u
Assumption log.
Described in Section 4.1.3.2. Schedule performance may indicate the need to revise
assumptions on activity sequencing, durations, and productivity.