Assumption log.
Described in Section 4.1.3.2. New assumptions and constraints may be added, and the status
of existing assumptions and constraints may be updated or closed out.
u
u
Lessons learned register.
Described in Section 4.4.3.1. Any lessons learned that will improve performance for
current or future projects is recorded as it is learned.
u
u
Requirements documentation.
Described in Section 5.2.3.1. New requirements may be identified during this
process. Progress on meeting requirements can also be updated.
u
u
Risk register.
Described in Section 11.2.3.1. New risks may be identified and existing risks may be updated
during this process. Risks are recorded in the risk register via risk management processes.
u
u