Part I: BIDDING PROCEDURES 3
Section II: Bid Data Sheet 31
Section III: Evaluation and Qualification Criteria 35
Section IV: Bidding Forms 47
Section V - Eligible Countries 74
Part II : REQUIREMENTS 75
Section VI - Employer’s Requirement (ERQ) 76
Section VII - Activity Schedule (ACS) 77
PART III – CONDITIONS OF CONTRACT AND CONTRACT FORMS 79
Section VIII: General Conditions of Contract 80
1. Definitions 85 81
2. Interpretation 88 81
3. Law and Language 89 81
4. Contract Agreement 89 81
5. Use of Contractor’s Documents 90 81
6. Contractor’s Use of Employer’s Documents 91 81
7. Assignment 91 81
8. Care and Supply of Documents 91 81
9. Confidential Details 91 81
10. Compliance with Laws 92 81
11. Joint and Several Liability 92 81
12. Contractor’s Representative 93 81
13. The Employer’s Representative 93 81
14. Delegation 94 81
15. Communications 94 81
16. Subcontracting 95 81
17. Other Contractors 95 81
18. Personnel and Equipment 95 81
19.Indemnities 96 81
20. Intellectual and Industrial Property Rights 97 81
21. Employer’s Risks 98 81
22. Contractor’s Risks 99 81
23. Insurance 99 81
24. Site Data and Reports 102 81
25. Contractor to Construct the Works 102 81
26. Works to Be Completed within intended Completion Date 102 81
27. Design by Contractor 103 81
28. Safety, Security and Protection of the Environment 105 81
29. Discoveries 106 81
30. Possession of the Site and it’s Access 107 81
31. Access Route and Transport of Goods 107 81
32. Determinations 108 81
33. Instructions, Inspections and Audits 108 81
34. Employer’s Claims 109 81
35.Contractor’s Claims 109 81
36. Dispute Settlement 112 81
37. Dispute Settlement by Arbitration 112 81
38. Staff, Labour and theirs facilities 112 81
39. Child Labor 114 81
40. Non-discrimination and Equal Opportunity 114 81
41. Program and Progress 115 81
42. Extension of the Intended Completion Date 117 81
43. Acceleration 117 81
44. Delays Ordered by the Employer 117 81
45. Management Meetings 117 81
46. Early Warning 117 81
47. Quality Assurance 118 82
48. Tests 119 82
49. Correction of Defects 120 82
50. Uncorrected Defects 121 82
51. Contract Price 122 82
52. Changes in the Contract Price 123 82
53. Variations 123 82
54. Cash Flow Forecasts 124 82
55. Interim Payment Certificate 124 82
56. Payments 126 82
57. Tax 127 82
58. Currency 127 82
59. Price Adjustment 127 82
60. Retention 127 82
61. Liquidated Damages 127 82
62. Bonus 127 82
63. Advance Payment 128 82
64. Securities 128 82
65. Day works 129 82
66. Cost of Repairs 130 82
67. Definition of Force Majeure 130 82
68. Notice of Force Majeure 130 82
69. Duty to Minimize Delay 130 82
70. Consequences of Force Majeure 131 82
71. Force Majeure Affecting Subcontractor 131 82
72. Optional Termination, Payment and Release 131 82
73. Release from Performance 132 82
74. Test on Completion 132 82
75. Tests after Completion 134 82
76. Taking Over of the Works 136 82
77. Final Account 137 82
78. Operating and Maintenance Manuals 138 82
79. Termination by Employer 139 82
80. Contractor’s Entitlement to Suspend Work 141 82
81. Termination by Contractor 142 82
82. Cessation of Work and Removal of Contractor’s Equipment 142 82
83. Payment upon Termination 142 82
84. Fraud and Corruption 143 82
85. Black Listing 144 82
86. Release from Performance 144 82
87. Suspension of DP Loan/Credit/Grant 145 82
88. Eligibility 145 82
89. Quarries and Spoil Dumps 145 82
90. Local Taxation 146 82
91. Value Added Tax 146 82
92. Income Taxes on Staff 146 82
93. Duties, Taxes and Royalties 146 82
94. Member of Government, etc, not Personally Liable 147 82
95. Compliance with Regulations for Explosives 147 82
96. Permission for Blasting 147 82
97. Records of Explosives 147 82
98. Traffic Diversion 148 82
1. Definitions 84 83
2. Interpretation 87 83
3. Law and Language 88 83
4. Contract Agreement 88 83
5. Use of Contractor’s Documents 89 83
6. Contractor’s Use of Employer’s Documents 90 83
7. Assignment 90 83
8. Care and Supply of Documents 90 83
9. Confidential Details 90 83
10. Compliance with Laws 91 83
11. Joint and Several Liability 91 83
12. Contractor’s Representative 92 83
13. The Employer’s Representative 92 83
14. Delegation 93 83
15. Communications 93 83
16. Subcontracting 94 83
17. Other Contractors 94 83
18. Personnel and Equipment 94 83
19.Indemnities 95 83
20. Intellectual and Industrial Property Rights 96 83
21. Employer’s Risks 97 83
22. Contractor’s Risks 98 83
23. Insurance 98 83
24. Site Data and Reports 100 83
25. Contractor to Construct the Works 101 83
26. Works to Be Completed within intended Completion Date 101 83
27. Design by Contractor 102 83
28. Safety, Security and Protection of the Environment 104 83
29. Discoveries 105 83
30. Possession of the Site and it’s Access 106 83
31. Access Route and Transport of Goods 106 83
32. Determinations 107 83
33. Instructions, Inspections and Audits 107 83
34. Employer’s Claims 108 83
35.Contractor’s Claims 108 83
36. Dispute Settlement 110 83
37. Dispute Settlement by Arbitration 111 83
38. Staff, Labour and theirs facilities 111 83
39. Child Labor 113 83
40. Non-discrimination and Equal Opportunity 113 83
41. Program and Progress 113 83
42. Extension of the Intended Completion Date 115 83
43. Acceleration 115 83
44. Delays Ordered by the Employer 116 83
45. Management Meetings 116 83
46. Early Warning 116 83
47. Quality Assurance 116 83
48. Tests 118 83
49. Correction of Defects 118 84
50. Uncorrected Defects 120 84
51. Contract Price 120 84
52. Changes in the Contract Price 121 84
53. Variations 122 84
54. Cash Flow Forecasts 123 84
55. Interim Payment Certificate 123 84
56. Payments 125 84
57. Tax 125 84
58. Currency 125 84
59. Price Adjustment 125 84
60. Retention 125 84
61. Liquidated Damages 125 84
62. Bonus 126 84
63. Advance Payment 127 84
64. Securities 127 84
65. Day works 128 84
66. Cost of Repairs 129 84
67. Definition of Force Majeure 129 84
68. Notice of Force Majeure 129 84
69. Duty to Minimize Delay 129 84
70. Consequences of Force Majeure 129 84
71. Force Majeure Affecting Subcontractor 130 84
72. Optional Termination, Payment and Release 130 84
73. Release from Performance 131 84
74. Test on Completion 131 84
75. Tests after Completion 133 84
76. Taking Over of the Works 135 84
77. Final Account 136 84
78. Operating and Maintenance Manuals 137 84
79. Termination by Employer 138 84
80. Contractor’s Entitlement to Suspend Work 140 84
81. Termination by Contractor 140 84
82. Cessation of Work and Removal of Contractor’s Equipment 141 84
83. Payment upon Termination 141 84
84. Fraud and Corruption 142 84
85. Black Listing 143 84
86. Release from Performance 143 84
87. Suspension of DP Loan/Credit/Grant 143 84
88. Eligibility 143 84
89. Quarries and Spoil Dumps 144 84
90. Local Taxation 144 84
91. Value Added Tax 145 84
92. Income Taxes on Staff 145 84
93. Duties, Taxes and Royalties 145 84
94. Member of Government, etc, not Personally Liable 145 84
95. Compliance with Regulations for Explosives 146 84
96. Permission for Blasting 146 84
97. Records of Explosives 146 84
98. Traffic Diversion 146 84
Section IX: Special Conditions of Contract 149
Section X: Contract Forms 156