Lessons learned register.

 Described in Section 4.4.3.1. The lessons learned register is updated with information 

on challenges encountered and how they could have been avoided as well as approaches that worked well for 

the development of the team.

u

u



Project schedule. 

Described in Section 6.5.3.2. Activities to develop the project team may result in changes to 

the project schedule.

u

u



Project team assignments.

 Described in Section 9.3.3.1. When team development results in changes to agreed-

upon assignments, these changes are recorded in the project team assignments documentation.

u

u



Resource calendars.

 Described in Section 9.2.1.2. Resource calendars are updated to reflect the availability of 

resources for the project.

u

u



Team charter. 

Described in Section 9.1.3.2. The team charter may be updated to reflect changes to agreed-upon 

team operating guidelines that result from team development.

9.4.3.5 ENTERPRISE ENVIRONMENTAL FACTORS UPDATES

Enterprise environmental factors that are updated as a result of the Develop Project Team process include but are 

not limited to:

u

u

Employee development plan records, and



u

u

Skill assessments.



9.4.3.6 ORGANIZATIONAL PROCESS ASSETS UPDATES

Organizational process assets that are updated as a result of the Develop Team process include but are not limited to:

u

u

Training requirements, and



u

u

Personnel assessment.




��

345


9.5 MANAGE TEAM

Manage Team is the process of tracking team member performance, providing feedback, resolving issues, and 

managing team changes to optimize project performance. The key benefit of this process is that it influences team 

behavior, manages conflict, and resolves issues. This process is performed throughout the project.

The inputs, tools and techniques, and outputs of the process are depicted in Figure 9-12. Figure 9-13 depicts the data 

flow diagram for the process.




Download 5,05 Mb.

Do'stlaringiz bilan baham:
1   ...   424   425   426   427   428   429   430   431   ...   1107




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©hozir.org 2024
ma'muriyatiga murojaat qiling

kiriting | ro'yxatdan o'tish
    Bosh sahifa
юртда тантана
Боғда битган
Бугун юртда
Эшитганлар жилманглар
Эшитмадим деманглар
битган бодомлар
Yangiariq tumani
qitish marakazi
Raqamli texnologiyalar
ilishida muhokamadan
tasdiqqa tavsiya
tavsiya etilgan
iqtisodiyot kafedrasi
steiermarkischen landesregierung
asarlaringizni yuboring
o'zingizning asarlaringizni
Iltimos faqat
faqat o'zingizning
steierm rkischen
landesregierung fachabteilung
rkischen landesregierung
hamshira loyihasi
loyihasi mavsum
faolyatining oqibatlari
asosiy adabiyotlar
fakulteti ahborot
ahborot havfsizligi
havfsizligi kafedrasi
fanidan bo’yicha
fakulteti iqtisodiyot
boshqaruv fakulteti
chiqarishda boshqaruv
ishlab chiqarishda
iqtisodiyot fakultet
multiservis tarmoqlari
fanidan asosiy
Uzbek fanidan
mavzulari potok
asosidagi multiservis
'aliyyil a'ziym
billahil 'aliyyil
illaa billahil
quvvata illaa
falah' deganida
Kompyuter savodxonligi
bo’yicha mustaqil
'alal falah'
Hayya 'alal
'alas soloh
Hayya 'alas
mavsum boyicha


yuklab olish