Not-to-exceed time and materials.
Customers incur unwanted risk from a traditional
time and materials
approach. One alternative is to limit the overall budget to a fixed amount. This allows the customer to incorporate
new ideas and innovations into the project not originally planned. When customers want to incorporate new
ideas, they will have to manage to a given capacity, replacing original work with new work. Work should be
closely monitored as hours allocated reach their limit. Also, additional contingency hours could be planned into
the maximum budget if considered helpful.