Organising for safety
55
➤
Any relevant British/European standard, e.g. BS
5839 Part 1/fi re detection and fi re alarm sys-
tems in buildings.
3.9.2 Construction Phase plan
A Construction Phase plan is essentially a collection of
information about the signifi cant health, safety, environ-
mental and fi re risks of the project. The plan will initially
be based upon information provided by the client, the
designer and the coordinator’s own assessment of the
risks inherent in the project, and will provide the health
and safety management plan during the construction
phase.
The initial plan
should include:
➤
A general description of the nature of the project
and intended completion times
➤
Information regarding the existing structure and
environment. This will include fi re hazard information
from the client
➤
Details of the organisation for fi re safety manage-
ment and liaison during the project
➤
Details of signifi cant risks which cannot be avoided
at the design stage and any fi re risks created by the
design or specifi cation of the structure
➤
Information regarding the overlap with the client’s
undertaking including the arrangements for fi re
emergency and any other site rules laid down by the
client, e.g. smoking policy
➤
Other safety information, e.g. means of escape in
case of fi re and fi re fi ghting facilities, signage rating
to the arrangements for highly fl ammable liquids and
liquefi ed petroleum gases.
This will amount to a list of hazards for which the princi-
pal contractor must develop suitable control measures.
Health and safety fi le
The CDM coordinator has the legal duty under CDM to
ensure that the health and safety fi le is compiled for the
completed building and mechanical and electrical serv-
ices, etc. within. The fi le is then handed to the client on
completion of the project. The client must then ensure
that the fi le is kept safe and is available for any inter-
ested party in the future.
The purpose of the health and safety fi le is to
provide all of the relevant details regarding the structure
and services, etc. within to anyone who in the future
may be carrying out further construction work, repairs,
maintenance or refurbishment of the building or facility.
The precise content of the fi le will depend upon the
nature and complexity of the structure. However, the
information contained in the fi le will be provided in part
by the designer and in part by the principal contractor
and, in reality, it may well be that the bulk of the work in
compiling the fi le will be done by the principal contractor
as they will be in fi rst capture of the information.