Defining rehabilitating ways and means of environment to previous condition
Short-term stopping or repair works of communications of treatment facility
In case of temporal stopping or repairing works (ongoing and capital), exploitation service of the objects is obliged to carry out operation plan connected with temporal stopping or repairing of work, which must in the first place, include security requirements and must be agreed with all interested legal persons.
Long-term stopping or conservation of operation of treatment facility
In case of long-term stopping or conservation of exploitation, exploitation service is obliged to form liquidation body, which will work on long-term stopping or conservation of the exploitation. The plan of long-term stopping or conservation of exploitation must be agreed with plenipotentiary bodies. The essential content of the plan represents safety requirements.
Liquidation of sewage systems
In case of liquidation of systems or their partial objects, special project must be carried out for defining rehabilitating ways and means of environment before previous condition.
Water-pipe and sewage operation service is responsible for carrying out the mentioned project. In accordance of the existing rule, special project of liquidation of objects must be agreed by plenipotentiary bodies and information must be send to all physical and legal persons.
Rules and regulations of stopping technological processes, dismantling buildings and equipments, rules and terms of carrying out dismantling works, environmental activities and security protection, rules and terms of render harmless and location of hazardous wastes, re-cultivation works and others must be foreseen in the project.
Residual impact
According to the present estimation, residual impact of high or middle level on environment caused by rehabilitation works is not expected. In accordance of international methodology, waste impact of low level is not submitted to be discussed.
Cumulative impact
Cumulative impact is not expected, there are no other facilities which may have impacts on the same “receptors” in vicinity of the project area.
Motor-car access roads
Existing road is used during construction of treatment facilities, which will be graveled in order to prevent further damage to the soil and improve the safety level. The construction site will be graveled during construction period and after the construction of temporary access roads will be cancelled roads necessary for operation will be left only.
On June 16, 2011 in c. Mtskheta in administrative building of Mtskheta Municipality Governance public discussion of the project named “Rehabilitation of sewage system of c. Mtskheta” about the calculation of Environmental Impact Assessment (EIA) was held. Information about the scheduled public discussion was published in the newspaper “24 saati” (#89, 28.04.2011 sec), as well as the Municipal Development Fund, Ltd. Gergili and Aarhus Center web pages.
The followings were present: representatives of Municipal Development Fund of Georgia (MDFG); “Gergili” LTD- environmental consultation firm; Mtskheta Municipality Governance; “Mtskheta Water” LTD, Non-government sector (NGOs) - association “Development of Civil Society”; association “Green Alternative”; representatives of local population. After presentation of calculation of estimation of impact on environment participants of public discussion had opportunity to express their opinions and remarks. Representatives of local municipality as well as representatives of non-government sector took active part in the discussion. Participants noted, that fulfillment of the project is important in the view of development of infrastructure and improvement of ecological and sanitation condition of c. Mtskheta. Though notes connected with fulfillment of the project and preliminary calculation prepared by EIA were also expressed, in particular these notes referred to analysis of alternatives of the placement of clean-up, location of replacement of collector, differences between EIA and Project resume, presented at the public review in terms of number of population and the treatment facility efficiency parameters and possibility of flooding, fire emergency or man mistake. Participants of discussion were given explanations, and their remarks were foreseen in the present estimation. Protocol expressing results of public discussion is enclosed with the EIA.
The information obtained as a result of the public review was processed and reflected in the final version of the document. In this regard additional public consultation was held for the revised version of this report taking the World Bank requirements into consideration. .A more advanced draft of this document was re-disclosed in-country through daily newspaper “24 saati” 2011.12.10, also information was published on the Web-sites of MDF, Ltd. “Gergili” and Aarhus Centre Georgia, and another consultation meeting was held on 19th December, 2011. The Meeting Minutes for both public consultations are attached on this EIA report.
The detailed information about issues discussed during above mentioned public hearings is presented in attachment #2 (Minutes of public consultation meetings 1 and 2).
9. Environmental Management Plan
9.1 Institutional set-up for EMP Implementation
MDFG is responsible for the implementation of the Environmental Management Plan (EMP). This responsibility includes obligation of qualitative and timely implementation of all mitigation measures included in the plan, supervision on implementation, documentation of the results of the supervision and calculations about these results in presence of supervision board of MDFG, regional development and the World Bank. MDFG will be responsible for local environmental bodies as well, local community and for communication with constructing contractors about cases such as environmental problems connected with implementation of environmental activities and manual principles for contractors.
Do'stlaringiz bilan baham: |