in estimating team and physical resources required for each activity on the activity list. Examples of attributes
323
u
u
Assumption log.
Described in Section 4.1.3.2. The assumption log may have information on productivity factors,
availability, cost estimates, and approaches to work that will influence the nature and number of team and
physical resources.
u
u
Cost estimates.
Described in Section 7.2.3.1. The cost of resources may impact
resource selection from the
quantity and skill level perspectives.