The standard for project management



Download 5,05 Mb.
Pdf ko'rish
bet276/1107
Sana11.01.2022
Hajmi5,05 Mb.
#348685
1   ...   272   273   274   275   276   277   278   279   ...   1107
Bog'liq
PMBOK Guide (6th Edition)

Tools & Techniques

Inputs

Outputs

Estimate Activity Durations

.1  Expert judgment

.2  Analogous estimating

.3  Parametric estimating

.4  Three-point estimating

.5  Bottom-up estimating

.6  Data analysis

• 

Alternatives analysis



• 

Reserve analysis

.7  Decision making

.8 Meetings

.1  Project management plan

• 

Schedule management plan



• 

Scope baseline

.2  Project documents

• 

Activity attributes



• 

Activity list

• 

Assumption log



• 

Lessons learned register

• 

Milestone list



• 

Project team assignments

• 

Resource breakdown



  structure

• 

Resource calendars



• 

Resource requirements

• 

Risk register



.3  Enterprise environmental    

 factors


.4  Organizational process assets

.1  Duration estimates

.2  Basis of estimates

.3  Project documents updates

• 

Activity attributes



• 

Assumption log

• 

Lessons learned register




196 

  

Part 1 - Guide

• Project

   charter

6.4

Estimate Activity



Durations

Enterprise/

Organization

• 

D



uration estimates

•  Basis of estimates

Project management plan

• Schedule management plan

• Scope baseline

Project documents

• 

A

ctivity attributes



• 

A

ctivity list



• 

A

ssumption log



• Lessons learned register

• 

M



ilestone list

• Project team assignments

• Resource breakdown structure

• Resource calendars

• Resource requirements

• 

R



isk register

•  Enterprise environmental factors

•  Organizational process assets

Project


Documents

Project


Management

Plan


Project

Documents

Project document updates

• 

A



ctivity attributes

• 

A



ssumption log

• Lessons learned register



Figure 6-13. Estimate Activity Durations: Data Flow Diagram

Estimating activity durations uses information from the scope of work, required resource types or skill levels, 

estimated resource quantities, and resource calendars. Other factors that may influence the duration estimates include 

constraints imposed on the duration, effort involved, or type of resources (e.g., fixed duration, fixed effort or work, fixed 

number of resources), as well as the schedule network analysis technique used. The inputs for the estimates of duration 

originate from the person or group on the project team who is most familiar with the nature of the work in the specific 

activity. The duration estimate is progressively elaborated, and the process considers the quality and availability of the 

input data. For example, as more detailed and precise data are available about the project engineering and design work, 

the accuracy and quality of the duration estimates improve.



197

The Estimate Activity Durations process requires an estimation of the amount of work effort required to complete 

the activity and the amount of available resources estimated to complete the activity. These estimates are used to 

approximate the number of work periods (activity duration) needed to complete the activity using the appropriate project 

and resource calendars. In many cases, the number of resources that are expected to be available to accomplish an 

activity, along with the skill proficiency of those resources, may determine the activity’s duration. A change to a driving 

resource allocated to the activity will usually have an effect on the duration, but this is not a simple “straight-line” or 

linear relationship. Sometimes, the intrinsic nature of the work (i.e., constraints imposed on the duration, effort involved, 

or number of resources) will take a predetermined amount of time to complete regardless of the resource allocation 

(e.g., a 24-hour stress test). Other factors for consideration when estimating duration include:

u

u


Download 5,05 Mb.

Do'stlaringiz bilan baham:
1   ...   272   273   274   275   276   277   278   279   ...   1107




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©hozir.org 2024
ma'muriyatiga murojaat qiling

kiriting | ro'yxatdan o'tish
    Bosh sahifa
юртда тантана
Боғда битган
Бугун юртда
Эшитганлар жилманглар
Эшитмадим деманглар
битган бодомлар
Yangiariq tumani
qitish marakazi
Raqamli texnologiyalar
ilishida muhokamadan
tasdiqqa tavsiya
tavsiya etilgan
iqtisodiyot kafedrasi
steiermarkischen landesregierung
asarlaringizni yuboring
o'zingizning asarlaringizni
Iltimos faqat
faqat o'zingizning
steierm rkischen
landesregierung fachabteilung
rkischen landesregierung
hamshira loyihasi
loyihasi mavsum
faolyatining oqibatlari
asosiy adabiyotlar
fakulteti ahborot
ahborot havfsizligi
havfsizligi kafedrasi
fanidan bo’yicha
fakulteti iqtisodiyot
boshqaruv fakulteti
chiqarishda boshqaruv
ishlab chiqarishda
iqtisodiyot fakultet
multiservis tarmoqlari
fanidan asosiy
Uzbek fanidan
mavzulari potok
asosidagi multiservis
'aliyyil a'ziym
billahil 'aliyyil
illaa billahil
quvvata illaa
falah' deganida
Kompyuter savodxonligi
bo’yicha mustaqil
'alal falah'
Hayya 'alal
'alas soloh
Hayya 'alas
mavsum boyicha


yuklab olish