Schedule management plan.
Described in Section 6.1.3.1. The schedule management plan may be updated to
reflect a change in the way the schedule was developed and will be managed.
u
u
Cost baseline.
Described in Section 7.3.3.1. Changes to the cost baseline are incorporated in response to
approved changes in scope, resources, or cost estimates. In some cases, cost variances can be so severe that a
revised cost baseline is needed to provide a realistic basis for performance measurement.
6.5.3.7 PROJECT DOCUMENTS UPDATES
Project documents that may be updated as a result of carrying out this process include but are not limited to: