Actual cost of work performed (ACWP) - This represents the total cost incurred for work done in a given period of time.
Actual duration - The length of time taken to complete an activity.
Actual effort - The amount of labor performed to complete an activity. It is expressed in person-hours or similar units of work.
Actual expenditure - The sum of costs paid from a budget.
Actual progress - This measures the amount of work completed on a project. It is used to assess the comparison between project progress and project baselines and is usually stated as a percentage.