Described in Section 9.2.3.1. Resource requirements identify the types and quantities
of resources required for each work package or activity.
u
Described in Section 11.2.3.1. The risk register contains details of individual project risks that
have been identified and prioritized, and for which risk responses are required. The risk register provides detailed
information that can be used to estimate costs.
7.2.1.3 ENTERPRISE ENVIRONMENTAL FACTORS
The enterprise environmental factors that can influence the Estimate Costs process include but are not limited to: