Control thresholds.
Variance thresholds for monitoring cost performance may be specified to indicate an
agreed-upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically
expressed as percentage deviations from the baseline plan.
u
u
Rules of performance measurement.
Earned value management (EVM) rules of performance measurement are
set. For example, the cost management plan may:
u
n
Define the points in the WBS at which measurement of control accounts will be performed;
u
n
Establish the EVM techniques (e.g., weighted milestones, fixed-formula, percent complete, etc.) to be
employed; and
u
n
Specify tracking methodologies and the EVM computation equations for calculating projected estimate at
completion (EAC) forecasts to provide a validity check on the bottom-up EAC.
u
u