Performance measurement baseline.
Described in Section 4.2.3.1. Changes to the performance measurement
baseline are incorporated in response to approved changes in scope, schedule performance, or cost estimates.
In some cases, the performance variances can be so severe that a change request is put forth to revise the
performance measurement baseline to provide a realistic basis for performance measurement.
5.6.3.4 PROJECT DOCUMENTS UPDATES
Project documents that may be updated as a result of carrying out this process include but are not limited to:
u
u