146.
The project site in Namangan province is located in the territory of Tashbulok city, and
will occupy an area of approximately 0.31 ha. The land, which is from the state land reserves,
was allocated to Toza Hudud in August 2019. It contains old facilities.
147.
The project site is mostly surrounded by industrial zones and open space. There are
however two small residential houses located close to the site. The nearest of these is located
about 15 meters away from the site perimeter, and about 55 meters
away from the location
of the proposed main service facility building. The layout of the service center will therefore
be designed in the way to allow for compliance with sanitary protection zone (buffer zone)
standards, that require that this distance be at least 50 meters. The site has necessary
utilities
including water supply, gas and electricity.
3.1.12 Namangan Service Center Site
Figure 15: L o ca tio n o f S e rvice C ente r in Nam angan P rovince
148.
The site also will be cleaned from existing buildings and facilities.
Figure 16: E x is tin g B u ild in g on th e
S ite Nam angan P rovince
3.1.13 T ash kent S e rvice C ente r Site
149.
The project site in Tashkent province is located in the Qizil Shalola settlement of
Kibray district, and occupies an area of 1 ha. It is located on the territory of a former tractor
park that has not been used for more than 10 years. In accordance with
the decision of the
39
Kibray district Khokimiyat, the site was transferred to the Toza Hudud in August 2019.
150.
There are small production activities to the south of the site,
and a private company
that segregates waste to the north-west of the site. From the west and north, the site is also
bordered with private houses. Due to the relatively large size of the site however (more than
1
ha), the layout of the service center will be designed in a way to ensure compliance with a
50 meter buffer zone from these properties (Figure 17). The site
has necessary utilities
including water supply, gas and electricity.
F igure 17: L o ca tio n o f S e rvice C ente r in T ash kent P rovince
151.
Although the site has reportedly been inactive for long time,
there are old buildings
and strewn garbage on the site. These will therefore be removed and the site cleaned prior
to commencement of service center construction (F igure 18).
Figure 18: E x is tin g B u ild in g on th e S ite in Tashkent P rovince
3.2
P ro je ct Im p le m e n ta tio n S chedule
152.
F igure 19 presents the implementation schedule for the project.
As shown, the
project is scheduled to commence in Q1 2020, and be completed by Q2 2024. Of relevance
to the IEE is the proposed schedule for the construction of the service centers, which is
shown in Output 4.4 to be between Q3 2020 and Q1 2022.
40