Contractor’s Documents means the calculations, computer programs and other software, drawings, manuals, models and other documents of a technical nature supplied by the Contractor under the Contract;
Contractor’s Bid is the completed bidding document submitted by the Contractor to the Employer.
Contract Price is the Accepted Contract Amount stated in the Letter of Acceptance and thereafter as adjusted in accordance with the Contract.
Commencement Date is given in the SCC. It is the latest date when the Contractor shall commence execution of the Design and Works. It does not necessarily coincide with any of the Site Possession Dates.
Days are calendar days; months are calendar-months.
Dayworks are varied work inputs subject to payment on a time basis for the Contractor’s employees and Equipment, in addition to payments for associated Materials and Plant.
Defect is any part of the Works not completed in accordance with the Contract.