Installation on Slopes
Place the mat 2 to 3 ft (0.66 – 1.0 m) over the
top of the slope and into an excavate end trench
measuring approximately 12-inch (30 cm) deep
by 6-inch (15 cm) wide. Pin the mat at 1-ft (0.3
m) intervals along the bottom of the trench,
backfill and compact. (See note above for
details of mat placement in trench.) Unroll the
mat down (or along) the slope maintaining
intimate contact between the soil and the mat.
Overlap adjacent rolls a minimum of 3-inch (7.5
cm). Pin the mat to the ground using staples or
pins in a 3-ft (1 m) center-to-center pattern.
Less frequent stapling/pinning is acceptable on
moderate slopes.