Large future investments.
The government expansion plans for the
sector summarized in Tables 2.10–2.13 will require substantial investment
(Table 2.15). For hydropower alone, the 22 projects laid out in Presidential
Resolution No. PP-2947 will require $2.2 billion. The government will fund 61%
of that, while external funding will provide the rest. Sources of external funding
include the Asian Development Bank, Asian Infrastructure Investment Bank,
and Eximbank China.
11
ADB. n.d. Projects. Uzbekistan: Advanced Electricity Metering Phase 4 Project. https://www.adb.org/
projects/41340-015/main#project-pds (accessed 16 July 2018).
67
Infrastructure as a Foundation for Job Creation
Table 2.15: Required Investment for Hydropower Plants, Uzbekistan
($ million)
Project
Cost
Source of Financing
Government
FDI and Lending
New Construction (11 projects)
1,730.5
1,195.6
534.9
Modernization
507.1
168.3
338.9
Total
2,237.6
1,363.9
873.8
FDI = foreign direct investment.
Source: Government of Uzbekistan (2017).
Huge investments are required to rehabilitate and extend the transmission and
distribution networks. Additional high-voltage transmission lines are needed
to supply electricity in the densely populated Fergana Valley. Where no large
power generation facilities exist, a circular transmission network should be
created to allow transmission within the country, and to further integrate
regional grids. In the short term, the government aims to construct six high-
voltage transmission lines that will cost about $570 million. The government
has estimated that a total of $1.3 billion will be needed for investments in
transmission and distribution systems by 2020. This will include modernizing
switchyards and constructing new distribution-level infrastructure, such as
advanced electrical meters for individual customers.
Uzbekenergo had also increased its long-term investment from
SUM1.3 billion to SUM1.5 billion to replace aging and inefficient generation
assets. In the past, the government has provided the investments. With the
huge investment requirement, funding from the public coffers will not suffice
and should be supplemented by private investments. However, private sector
participation in the power sector is currently negligible due to the sector’s poor
economic performance, and insufficient financing of the sector has stifled
the modernization and reconstruction of power infrastructure. Investment
directed to the electricity generation sector has been growing but at a slow
pace, accounting for just 3.5% of the total annual investments of the company
during 2007–2017.
Increasing investments through private funds requires adjusting electricity
tariffs to cover long-run supply costs. The tariff hikes since 2012 had enabled
the Uzbekenergo to slowly recover operating and maintenance costs and other
administrative expenses. The current electricity tariffs for all of Uzbekenergo’s
subsidiaries were on a cost basis to cover these costs. The 2018 tariff rates
are SUM178.40/kWh for industry and SUM228.60/kWh for residential users
68
Do'stlaringiz bilan baham: |