Test and Evaluation Documents.
Project documents that describe the activities used to determine if the product meets
the quality objectives stated in the quality management plan.
Threat.
A risk that would have a negative effect on one or more project objectives.
Three-Point Estimating. A
technique used to estimate cost or duration by applying an average or weighted average of
optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.
Threshold.
A predetermined value of a measurable project variable that represents a limit that requires action to be
taken if it is reached.