[insert additional clauses, if required]
GCC 37.1
|
The place of arbitration shall be: ……………………………. [insert place]
|
GCC 38.12
|
The list of Key Personnel and their Qualifications:
|
C. Time Control
|
GCC 41.1
|
The Contractor shall submit for approval a Program for the Works within ………[Insert days]days from the date of the Letter of Acceptance.
|
GCC 41.7
|
[insert the period of progress report required, other monthly progress reports]
|
D. Quality Control
|
GCC 49.1
|
The Defects Liability Period is: [insert 730 days or more as per required by Employer].
|
GCC 49.9
|
The Latent Defects Liability Period is (Applicable or Nonapplicable to be decided by the Employer): [If Applicable, insert …………days as required by Employer].
|
E. Cost Control
|
GCC 51.6
|
|