8.1.4
Prioritize stakeholder needs
The project team must condense, prioritize, and summarize the list of stakeholder
needs into a manageable collection that will be used to guide the specification of
software requirements. Stakeholder needs and expectations must be translated
into software requirements for the product (computing environment and software
application) and post-development processes. An individual stakeholder need may
involve several requirements that the project will be held accountable for achiev-
ing. The level of effort and resources necessary to fulfill a stakeholder need must
be determined, and the project and technical risks must be included in the cost esti-
mates. The project budget can then be allocated against the prioritized needs. This
establishes the initial scope of the software development effort and provides the
basis for project and technical planning.