Microsoft Word pcr uzb public Finance Management Reform Project Final 7Sept2017. docx


Package 3: Supply of computers and networking equipment for treasury



Download 287,68 Kb.
Pdf ko'rish
bet9/36
Sana08.03.2022
Hajmi287,68 Kb.
#486196
1   ...   5   6   7   8   9   10   11   12   ...   36
Bog'liq
Uzbekiston finance

Package 3: Supply of computers and networking equipment for treasury 
offices.
This package covered the procurement of 580 computers, printers, 
related local servers, and electronic security facilities for the treasury offices. 
These items were to be used for standard office functions and to access MOF’s 
interim Treasury One software system, and subsequently to be available for use 
with the GFMIS. 
(iv) 
Package 4: Further computers and networking equipment for treasury 
offices.
This package was to procure 1,048 computers (including uninterruptible 
power supplies and office software) to fully equip provincial and district treasury 
offices by the time the GFMIS application was ready for pilot testing. 
(v) 
Package 5: Supply of telecommunication networking equipment.
This 
package covered the networking equipment (including routers, firewalls, and 
internet telephony devices) required to interconnect all treasury locations. 
(vi) 
Package 6: Local support systems.
This package covered the supply and 
installation of cabling, local area network switches, telecommunications cabling, 
uninterruptible power supplies, fiber-optic connections, alarm and monitoring 
systems, and fire detection and suppression equipment. 
13. 
Procurement of the six packages was to be financed by the ADB loan and procured 
through international competitive bidding. However, Government repackaged the contracts in 
2008 to optimize procurement by combining six contracts into three new contract packages. 
11
Ministry of Finance of the Republic of Uzbekistan. Treasury Division (organizational structure). 
https://www.mf.uz/media/file_en/treasury/treasury_str.pdf




This delayed procurement further and resulted in ADB financing only two of the revised 
packages. 
14. 
Revised package 1 was to procure a commercial off-the-shelf GFMIS application 
software and main servers. ADB used a two-stage bidding procedure for the package, with 
bidding announced in December 2009. Bid opening was originally planned for March 2010 but 
was postponed to 28 April 2010. The evaluation of technical proposals took longer than 
expected and was completed in May 2011. The delays resulted from the need to finalize 
technical requirements, the use of a complex procurement procedure, and a slow evaluation 
process. Executing agency staff was unfamiliar with the two-stage bidding procedure. On 
occasion, this led to different interpretations of ADB procedures and bidding documents 
between the executing agency’s evaluation team and the ADB team. Three bidders were found 
technically responsive and passed to the second stage, and another three were requested to 
submit price proposals and revised technical proposals. Only one bidder submitted its proposal 
for the second stage in June 2011. The bidder’s price proposal was 43% above the budget and 
the executing agency’s bid committee rejected the proposal and suggested rebidding in August 
2011. In September 2011, the executing agency requested ADB to consider rebidding for this 
package. The assessment for the rebidding timeline indicated that rebidding may result in a 2- 
or 3-year loan extension to complete procurement and execute the contract. Given the 
uncertainties associated with rebidding, ADB did not agree with the proposal.
12
Alternative 
options were sought by the Project Steering Committee (PSC), which decided to split the 
package into two contracts, separating procurement of hardware and software development. 
The executing agency proposed to finance the development of a GFMIS software based on 
Treasury-4, the Treasury’s existing application software.
13
The executing agency assessment 
showed that Treasury-4 has 80 percent of the required functional requirements envisioned 
under a new GFMIS. Thus, the executing agency proposed to change the approach and 
develop Treasury-4 into a modernized in-house application using the already approved 
schedule of technical requirements for the GFMIS. These were to be financed in 2013–2015 
from the state budget following government procurement procedures. The loan amount related 
to this package ($10.4 million) was canceled along with savings (para. 22). 
15. 
During 2013–2017, ADB’s further involvement with the procurement of revised package 
1 stopped because the loan was closed. ADB did not provide financing for this package. In 2013, 
the executing agency, using the schedule of technical requirements for software and hardware 
developed under the project, split GFMIS procurement into two contracts: (i) procurement from 
local software developers for services to complete the transformation of Treasury-4 into a 
modernized GFMIS with software support until 2023, and (ii) procurement of main and backup 
servers from international suppliers.
14
Some changes resulted in the need for the MOF to 
prepare new budget requirements and seek budget approvals to fund the software development 
costs and the equipment. In 2013–2014, two bid opportunities using the national procurement 
system were organized by the MOF for GFMIS software development and server procurement. 
The procurement of servers was funded by the 2014 and 2015 state budget, with installation 
commencing in June 2015. The procurement of software developer services took longer. After 
receiving three bids, the MOF selected an Uzbek IT firm and Treasury-4 developer to design 
and develop the GFMIS. The process was expected to be completed by 2015. However, delays 
in contract signing resulted in development taking place in 2015–2016. The modified GFMIS 
12
Rebidding could have resulted in need for loan extension for at least 3 years. 
13
Treasury-4 is an upgraded software package run by the Treasury during 2007–2011 to ensure operations. It was 
supposed to be replaced by the new GFMIS procured under the project. 
14
The technical requirements were developed under ADB-funded TA on Supporting Public Finance Management 
Reform. 



was ready for testing in February 2017 in one selected province and one district and is expected 
to be rolled out in the remaining provinces beginning in June 2017. 
16. 
Revised package 2 was to procure computers and office equipment for the treasury 
offices. Revised package 3 was to procure telecommunications equipment, local area 
networking, infrastructure equipment, and support systems. ADB loan proceeds were used to 
procure these packages. The executing agency initially decided to postpone procurement of 
these packages as it wanted to first procure the GFMIS contract package. This decision delayed 
the process. Bidding documents were approved in May 2011, bid proposals were opened in July 
2011, and proposal evaluation was completed in August 2011. In November 2011, ADB issued 
no-objection letters to contract awards for both packages. The contracts totaled $6.194 million 
and were submitted to ADB on 27 December 2011. ADB and the PMO developed a detailed 
contracts implementation plan to ensure timely delivery of goods and related services before the 
loan closing date. The delivery of goods was completed as planned. 
17. 
ADB also provided consulting services under the associated TA grant to help prepare 
the technical requirements of; bidding documents for; and revised budget, revenue, functional, 
and economic classification of state budget expenditures for all packages.
15
18. 

Download 287,68 Kb.

Do'stlaringiz bilan baham:
1   ...   5   6   7   8   9   10   11   12   ...   36




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©hozir.org 2024
ma'muriyatiga murojaat qiling

kiriting | ro'yxatdan o'tish
    Bosh sahifa
юртда тантана
Боғда битган
Бугун юртда
Эшитганлар жилманглар
Эшитмадим деманглар
битган бодомлар
Yangiariq tumani
qitish marakazi
Raqamli texnologiyalar
ilishida muhokamadan
tasdiqqa tavsiya
tavsiya etilgan
iqtisodiyot kafedrasi
steiermarkischen landesregierung
asarlaringizni yuboring
o'zingizning asarlaringizni
Iltimos faqat
faqat o'zingizning
steierm rkischen
landesregierung fachabteilung
rkischen landesregierung
hamshira loyihasi
loyihasi mavsum
faolyatining oqibatlari
asosiy adabiyotlar
fakulteti ahborot
ahborot havfsizligi
havfsizligi kafedrasi
fanidan bo’yicha
fakulteti iqtisodiyot
boshqaruv fakulteti
chiqarishda boshqaruv
ishlab chiqarishda
iqtisodiyot fakultet
multiservis tarmoqlari
fanidan asosiy
Uzbek fanidan
mavzulari potok
asosidagi multiservis
'aliyyil a'ziym
billahil 'aliyyil
illaa billahil
quvvata illaa
falah' deganida
Kompyuter savodxonligi
bo’yicha mustaqil
'alal falah'
Hayya 'alal
'alas soloh
Hayya 'alas
mavsum boyicha


yuklab olish