258
Part 1 - Guide
• Project
charter
4.3
Direct and
Manage
Project Work
7.3
Determine
Budget
•
W
ork performance data
Project management plan
• Cost management plan
• Cost baseline
• Performance measurement baseline
• Lessons learned register
• Project funding requirements
Project
Management
Plan
Project
Documents
Project
Documents
4.6
Perform
Integrated
Change Control
4.5
Monitor and
Control
Project Work
7.4
Control
Costs
Enterprise/
Organization
• Organizational process assets
• Change requests
• Cost forecasts
•
W
ork performance information
Project management
plan updates
• Cost management plan
• Cost baseline
• Performance measurement baseline
Project documents updates
• Assumption log
• Basis of estimates
• Cost estimates
• Lessons learned register
• Risk register
Project
Management
Plan
Figure 7-11. Control Costs: Data Flow Diagram
��
259
Updating the budget requires knowledge of the actual costs spent to date. Any increase to the authorized budget can
only be approved through the Perform Integrated Change Control process (Section 4.6). Monitoring the expenditure of
funds without regard to the value of work being accomplished for such expenditures has little value to the project, other
than to track the outflow of funds. Much of the effort of cost control involves analyzing the relationship between the
consumption of project funds and the work being accomplished for such expenditures. The key to effective cost control
is the management of the approved cost baseline.
Project cost control includes:
u
u
Influencing the factors that create changes to the authorized cost baseline;
u
u
Ensuring that all change requests are acted on in a timely manner;
u
u
Managing the actual changes when and as they occur;
u
u
Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS component, by
activity,
and in total for the project;
u
u
Monitoring cost performance to isolate and understand variances from the approved cost baseline;
u
u
Monitoring work performance against funds expended;
u
u
Preventing unapproved changes from being included in the reported cost or resource usage;
u
u
Informing appropriate stakeholders of all approved changes and associated cost; and
u
u
Bringing expected cost overruns within acceptable limits.
7.4.1 CONTROL COSTS: INPUTS
7.4.1.1 PROJECT MANAGEMENT PLAN
Described in Section 4.2.3.1. Project management plan components include but are not limited to:
u
u
Do'stlaringiz bilan baham: