Schedule management plan.
Described in Section 6.1.3.1. The schedule management plan identifies the
scheduling method and tool used to create the schedule and how the schedule is to be calculated.
u
u
Scope baseline.
Described in Section 5.4.3.1. The scope statement, WBS, and WBS dictionary have details about
the project deliverables that are considered when building the schedule model.
6.5.1.2 PROJECT DOCUMENTS
Project documents that can be considered as inputs for this process include but are not limited to:
u
u
Activity attributes.
Described in Section 6.2.3.2. The activity attributes provide the details used to build the
schedule model.
u
u
Activity list.
Described in Section 6.2.3.1. The activity list identifies the activities that will be included in the
schedule model.
u
u
Assumption log.
Described in Section 4.1.3.2. Assumptions and constraints recorded in the assumption log may
give rise to individual project risks that may impact the project schedule.