Case study №1
When designing the new settlement "Dashtobod" allocated 15 hectares of land. The site is located 1 km from the centers of breeding of malaria mosquitoes. Plan of the village consists of 5 elements: residential zone, industrial zone, municipal warehouse zone, external transport and green area. The gap between residential and industrial zone of 500 m. The production zone is located on the leeward side with respect to the housing lower terrain and open bodies of water downstream. The industrial zone is planned to build the machine building plant, which is equipped with electrostatic precipitators.
Question: Evaluate the accuracy of the new layout of the village.
Decision. Land with an area of 15 hectares set aside correct the master plan of the village meets the hygienic requirements. Location of the plant site in relation to the living right.
The site should be located 3 km away from the centers of breeding of malaria mosquitoes. SPZ meets the hygiene requirements of SanPiN №0006 - 93 as Machinery Plant belongs to class 4 and is equipped with electrostatic precipitators.
Case study number 2
When designing the new settlement "Ziff" allocated 12 hectares of land. The site is located 500 m from the pockets of breeding malarial mosquitoes. Plan of the village consists of 4 elements: residential zone, industrial zone, external transport and green zone. The gap between residential and industrial areas 100m. The production zone is located on the windward side with respect to the housing. The industrial zone is planned to build the plant with the steel cycle capacity of more than 1 million. M. / Year of pig iron and steel.
Question: Evaluate the accuracy of the new layout of the village.
Solution: Land with an area of 12 hectares allotted properly, the plan of the village does not meet the hygienic requirements as no communal storage area and landscape-recreational zone. Location of the plant site in relation to the residential is not right. The site should be located 3 km away from the centers of breeding of malaria mosquitoes. SPZ does not meet the hygiene requirements of SanPiN №0006 - 96 as Steel mill with a cycle capacity of more than 1 million. m. / year of iron and steel refers to the first class and the SPZ to be 1000 meters. The project also lacks treatment facilities.
Number 1.
When designing the new settlement "Quruvchi" allocated
20 hectares of land. The site is located 1500 meters from the centers of breeding
.malyariynyh mosquitoes. Plan of the village consists of 4 elements: residential zone, industrial zone, external transport and social center. The gap between residential and industrial area of 1000 m. The production zone is located on the windward side with respect to the housing. The industrial zone is planned construction works for the extraction of ores of mercury arsenic, manganese. The project does not provide treatment facilities. SPZ 500m.
Question. Rate the correct layout of the new village.
Number 2.
When designing the new settlement "Pakhtachi" allocated 2
hectares of land. The site is located 250 m from the pockets of breeding
malarial mosquitoes. Plan of the village consists of 4 elements: residential zone, industrial zone, external transport and social center. The gap between residential and industrial zone of 700 m. The production zone is located on the windward side with respect to the housing. The industrial zone is planned to construct 5 garment factories. Under the project all the factories are equipped with treatment facilities ie cyclone with the efficiency of 50 percent.
Question. Rate the correct layout of the new village.